Handover documentation and warranties

What has to be handed over at the end, and why it is gathered during rather than after.

Updated on 13/08/2026

Completion is the moment when everything generated over two years is demanded at once: installation certificates, material warranties, as-built drawings, test records, manuals. And whoever gathers it at the end discovers half of it belonged to a company that got paid and left.

Why it always jams the same way

DocumentWho holds itWhen it vanishes
Installation certificatesThe installerWhen their part finishes, months earlier
Material warrantiesThe supplier or buyerWhen that person moves project
As-built drawingsThe engineers or site managerWhen they move site
Test recordsWhoever ran them, sometimes only on paperWhen the site office is dismantled

Important

All four share something: **they exist while the work is fresh and evaporate when that trade leaves site.** Asking for them at the end means asking the worst person at the worst moment.

The rule that fixes it

Each trade hands over its documentation **when its part finishes, not when the project finishes**. And their final payment application closes with it delivered. It is the only lever that truly works, and it requires chasing nobody.

  1. 1

    Define the list per trade at contracting

    In the contract or order itself, not in a last-minute email.

  2. 2

    Open their folder from day one

    So that handing over means uploading, not preparing a package.

  3. 3

    Tie financial closure to delivery

    It is what turns a request into a priority.

  4. 4

    And review as each trade finishes, not at the end

    A wrong certificate is fixed in a week while they are still there; in a year, it is not.

Watch out

Beware accepting "I'll email it to you". What arrives by email to one person disappears with their inbox: if they move site or company, the completion documentation stayed in a mailbox nobody opens.

What the client takes away

That last point serves you too: a handover the client can navigate alone generates far fewer calls over the following two years.

Worth knowing

Warranties are documents with expiry dates like any other. Handed over with their dates, whoever receives the building can see what is still covered without opening every PDF.

What if a trade no longer exists?

Hence collecting as their part ends. After that you can only reconstruct what is available.

Does it apply to small refurbishments?

Yes, and it is easier: fewer trades and less turnover.

Who keeps it afterwards?

The client, and you should keep a copy for your liability period.

A real case

The situation

A developer gathers handover documentation three months after completion.

What you do

  1. Switches to collecting per trade as each part closes
  2. Ties the final payment application to document delivery

What you get

The next development hands over the complete set on the day of completion.

The situation

Close-out gathers months-old material at the end.

What you do

  1. Requests as each trade finishes

What you get

Close-out becomes a formality.

The situation

A trade has been paid and does not respond.

What you do

  1. Chases before certifying their work

What you get

You chase while there is still leverage.

The situation

The list of what is missing appears at the end.

What you do

  1. Shows what is missing from day one

What you get

The gap is visible while it can be closed.

The situation

Handover happens with a gap and no record of chasing.

What you do

  1. Keeps what was requested, from whom and how many times

What you get

The trail is the defence.

The situation

Under warranty, close-out documentation is requested.

What you do

  1. Keeps the file beyond handover

What you get

You answer with the record from then.