Structural material acceptance on site

What to check when the lorry arrives, because afterwards it is already installed.

Updated on 13/08/2026

Structural material has one feature that sets it apart: once it is in place, checking it costs a hundred times more. Anything not looked at during unloading becomes a demolition problem, not a paperwork one.

What arrives with the material and must be captured

ElementWhat it evidencesIf missing
Delivery note identifying the consignmentWhat arrived and from which heat or batchWithout it, nothing else can be linked to anything
Product certificateThat the material meets the specificationRequest it from the supplier, and it takes time
Marking and labelling on the material itselfThat what is on site is what the paper saysVisible at a glance, if someone looks
Test results, where applicableWhat was checked and with what resultThe lab issues them later: they must be chased

Important

The fourth row is the one left pending that nobody chases. Results arrive days after unloading, when the lorry has gone and the works have moved on — and if nobody linked them to the specific consignment, they turn up loose in an inbox and evidence nothing. A test without the consignment it belongs to is a nice-looking piece of paper.

How to do it without slowing unloading

  1. 1

    Photo of the delivery note and the marking, at unloading

    Thirty seconds on a phone, linked to the site and the date.

  2. 2

    The consignment as the thread

    Heat, batch or lot: it is what later links material, certificate and test.

  3. 3

    Pending tests, recorded as pending

    With who issues them and by when. Unrecorded, they are never chased.

  4. 4

    And rejections recorded too

    If something is sent back, that record is worth as much as the accepted material's.

Watch out

The expensive blind spot is material arriving when the responsible person is not there. A seven-in-the-morning or Saturday delivery is received by whoever is present, and without a two-minute route to record it from a phone, nothing remains: no photo, no legible note, no record of who accepted it. That is the gap through which nothing can be reconstructed later.

What gets asked months or years later

All four are answered from the site file if they were captured at unloading, and are unreconstructable otherwise. There is no middle ground: either it was caught then or it does not exist.

Worth knowing

It applies equally to structural steel, supplied concrete, precast elements and structural safety components. The tests and who signs them change; that the filing unit is the consignment, not the order or the invoice, does not.

What if the supplier sends certificates at month end?

That is normal: hence recording them as pending on the day of delivery.

Is it needed on small jobs?

The obligation depends on the project; the cost of doing it is the same and low.

Who should sign for acceptance?

Whoever holds that role on site, and their name should be recorded.

A real case

The situation

A site receives steel on a Saturday and the test results arrive by email two weeks later.

What you do

  1. Photographs the delivery note and marking at unloading, linked to the consignment
  2. Records the tests as pending with an expected date

What you get

When the supervising engineer asks, the test is tied to the consignment actually installed.

The situation

Material arrives and the delivery note is signed in a rush.

What you do

  1. Captures the note as it is signed

What you get

The paper stops being the only copy.

The situation

Material arrives without its documentation.

What you do

  1. Puts on record what is missing the same day

What you get

The claim goes out while it is easy.

The situation

Nobody notes which area each consignment went to.

What you do

  1. Records what was unloaded and where it was used

What you get

The data nobody else holds is kept.

The situation

At close-out, eight months of delivery documentation is requested.

What you do

  1. Keeps each delivery with its date

What you get

The handover is prepared in an afternoon.

The situation

A different reference to the one ordered arrives.

What you do

  1. Notes the difference on receipt

What you get

The discrepancy is resolved before installation.